Paving will continue on Monday, September 17 at 7 am (weather permitting) picking up at 68 Sandpiper Crescent, heading east to Merwin Avenue. Our contractor expects to COMPLETE ALL of Sandpiper Crescent and Sandpiper Circle in one day. ALL VEHICLES must be off the streets in those areas by 7am.

Based on time available (and weather) the common area parking spaces will be painted in Monday evening (17th) or Tuesday the 18th. There will be NO PARKING on ANY Surf Village street parking areas until the caution tape has been removed BY the contractor.

The installation of the concrete curbs is scheduled to start Friday, September 21st and continue through the following week. This should not cause any further inconvenience.
 
Thank you for your patience, we are almost finished!