Monday, August 6th and Tuesday, August 7th, driveway work will begin on Sandpiper Circle. All vehicles must be out of the garage and off the driveway by 7:00am. Your garage door needs to be left open so that the clean out in the floor of the garage can be inspected before the sewer lateral is installed. You will be able to use the driveway after 5:00pm.

Once Sandpiper Circle has been completed, the remaining 3 buildings on Sandpiper Crescent will follow. We cannot predict how fast the work will proceed, but we anticipate Unit #132 will be started by late Tuesday or 1st thing Wednesday morning.

It is also anticipated that the asphalt binder coat will be done on Friday, August 10th. You may drive on the asphalt to get your car into your garage one hour after the paving is completed. You should not park on the newly asphalted driveways for at least 2 days, not counting the day it is done. You should also not turn the car wheels on the surface. Thank you for your co-operation in helping this project run as smoothly as possible.