Current Projects

Roads, Curbs, Driveways Project

The Roads, Curbs, and Driveway Project will be starting in July and is expected to continue through October. The initial plans, which will start in mid July, call for the replacement of the sewer laterals on Sandpiper Crescent and Sandpiper Circle for those owners who have signed up and have paid for this replacement. Once this is completed, the driveways will be stripped of its asphalt and curbs will be excavated and removed. This work will be initiated from the Seahawk Court side of our community and continue around to the East entrance and will be completed by the end of August, early September. The roadways will then be milled and resurfaced. All existing asphalt curbing will be replaced with extruded concrete curbs. Announcements, information, and advisories will be periodically posted below.

Starting on Thursday, and through Friday this week, all cars must be removed from the Parking Areas and Roadways by 7:00am. The contractor will be removing curbing from the Roadways and Parking Areas and will require full access to all of these areas.

The binder (asphalt) work will begin next week in Seahawk Court. Please remember that you cannot drive on the new binder coat for 1 hour after it has been applied. Parking is not permitted for 2 days to allow the asphalt to cure. (Not counting the day of installation!) You can drive on the asphalt ONLY to park inside your garage.

The milling of the roadways will start after the Labor Day Holiday.

The binder (asphalt) work will begin today and possibly tomorrow in Sandpiper Circle and continue around Sandpiper Crescent to the Merwin Avenue entrance. Please remember that you cannot drive on the new binder coat for 1 hour after it has been applied. Parking is not permitted for 2 days to allow the asphalt to cure. (Not counting the day of installation!) You can drive on the asphalt in order to park inside your garage.

Work on the reconstruction of the road by 143 and 127 and Sandpiper cleanup will be completed this week.

Alert, all Merwin and Seahawk Owners- Starting next week on Monday, the contractor is on track to begin work on Seahawk Court. ALL vehicles must be moved from the Seahawk Court roadway and off of ALL driveways, including the parking spaces by 7:00am. There will be construction equipment and piles of stone stored in the parking area, which will be unusable.

Monday, August 6th and Tuesday, August 7th, driveway work will begin on Sandpiper Circle. All vehicles must be out of the garage and off the driveway by 7:00am. Your garage door needs to be left open so that the clean out in the floor of the garage can be inspected before the sewer lateral is installed. You will be able to use the driveway after 5:00pm.

Once Sandpiper Circle has been completed, the remaining 3 buildings on Sandpiper Crescent will follow. We cannot predict how fast the work will proceed, but we anticipate Unit #132 will be started by late Tuesday or 1st thing Wednesday morning.

It is also anticipated that the asphalt binder coat will be done on Friday, August 10th. You may drive on the asphalt to get your car into your garage one hour after the paving is completed. You should not park on the newly asphalted driveways for at least 2 days, not counting the day it is done. You should also not turn the car wheels on the surface. Thank you for your co-operation in helping this project run as smoothly as possible.

Driveways: At this time, all excavated driveways are being paved with a binder coat of asphalt. You may drive on it to get your car into your garage one hour after the paving is completed. You should not park on the newly asphalted driveways for at least 2 days, not counting the day that it is done. During this time, you should also not turn the car wheels on this surface. Work will be starting on Sandpiper Circle on Monday and then moving to complete the last 4 buildings. Thank you for your help and co-operation in making these major upgrades to the Surf Village Community.

The results of the ballots authorizing the loan for the road project were overwhelming, 94% approved and 5% against. The Board thanks the Community for their support. The loan was closed on August 1st, 2012.

ATTENTION ALL RESIDENTS!
Starting THIS Thursday August 2nd & Friday August 3rd all driveways that have been excavated will be paved with a binder coat of asphalt.

WHAT DO I HAVE TO DO?
ALL VEHICLES must be off the driveways by 7am. Vehicles may be left in garages but WILL NOT be able to exit while the work is in progress and while the asphalt is drying. You can drive on it after an hour, but you will NOT be able to park on the new asphalt for 2 days.

The paving will start at #7 & #10 Sandpiper Crescent & move around to the east. There is NO WAY to predict  how many driveways will be completed on Thursday, so please plan accordingly for both days.